As a subcontractor of the Czech company FLUID Engineering, we carried out the task of assembling pipelines constituting the cooling system for a new sheet metal galvanizing line in the Kraków branch of the ArcelorMittal Poland steelworks. The total length of the laid and welded pipelines was about 2 km. Carbon steel and stainless steel pipes with diameters from 50 mm to 273 mm were used.
Additionally, we prefabricated and assembled supporting structures for the above-mentioned installations with a total weight of about 25 tonnes.